This problem usually occurs because the foundation is not flat when making the swimming pool brick. After the swimming pool is filled with water, the walls generally have rapid flow, rapid seepage and slow seepage. Therefore, it is suggested to use three-layer plugging, combining rigid and flexible, and plugging construction on both inner and outer sides. Specific construction process for plugging:
1、 Material preparation: M131 water stop agent, quick setting water leakage, slow setting water leakage, water-soluble polyurethane grouting, composite waterproof coating.
2、 Work sequence: clean the base course - find the leakage point - chisel the leakage point - M131 quick setting plugging - observe the new leakage point - and continue plugging - water-soluble polyurethane grouting - apply retarding anti-seepage putty on the large surface - natural maintenance - apply flexible composite waterproof coating - quality acceptance.
1. Clean up the base course: clean up the accumulated water, shovel off the floating mortar on the wall, clean it with a steel wire brush and broom, and finally flush it with clean water. The cleaning work is serious and thorough.
2. Find the leakage point: the leakage phenomena of the swimming pool include slow seepage, fast seepage and torrent. Find the leakage point and mark it. It shall be accurate and targeted.
3. Chisel leakage point: the direct plugging method can be used for hole leakage. Generally, when the water pressure is small and the hole is small, the hole is chiseled with the leakage point as the center, with diameter x depth of 2x4, 3x6 and 4x8cm, large bottom and small mouth, and washed with water.
It must be that the foundation of the swimming pool was not flat when it was built. After the swimming pool was filled with water, there are usually rapids, rapid seepage and slow seepage on the walls. Therefore, it is suggested to use three-layer plugging, combining rigid and flexible, and plugging construction on both inner and outer sides. Specific construction process of plugging: I. material preparation: M131 water stop agent, no leakage of quick setting water, no leakage of slow setting water, water-soluble polyurethane grouting and composite waterproof coating. 2、 Operation sequence: clean the base course - find the leakage point - chisel the leakage point - M131 quick setting plugging - observe the new leakage point - and continue plugging - water-soluble polyurethane grouting - apply retarding anti-seepage putty on the large surface - natural maintenance - apply flexible composite waterproof coating - quality acceptance. 1. Clean up the base course: clean up the accumulated water, shovel off the floating mortar on the wall, clean it with a steel wire brush and broom, and finally flush it with clean water. The cleaning work is serious and thorough. 2. Find the leakage point: the leakage phenomena of this swimming pool include slow seepage, fast seepage and torrent. Find the leakage point and mark it. It shall be accurate and targeted. 3. Chisel the water leakage point: the direct plugging method can be used for the water leakage of the hole. Generally, when the water pressure is small and the hole is small, the hole is chiseled with the leakage point as the center, the diameter x depth is 2x4, 3x6 and 4x8cm, and the circular groove with large bottom and small mouth is washed with water.